House no 1 = funds already in hand for completion
House no 2 = £1,500
House no 3 = £5,600
House no 4 = £7,000
House no 5 = £10,000
House no 6 = £10,000
Total to Complete all of the Houses = £34,100
We will be having a meeting with Pastor Leonard and Vincent this week where we hope to confirm these costs as accurately as possible, given the fluctuating value of the pound and increasing costs of cement. We will also try and give the costs associated with the additional items listed below after we have had that meeting.
There is always the possibility that we may be able to sell the truck that was purchased last year for transporting materials to site. This might raise around £7,000. We are concerned, however, that this might be only a short term solution (and a little short sighted) and it might end up costing us more as we pay to have materials transported to site, but at the moment we are considering this as a possible means of raising some immediate finance for the project.
The following is also required.
Water to the site:
There is mains water available in Gatumba and to have this piped to the site will be = £2,000
Electricity to the site:
There is mains electricity available in Gatumba and to have this delivered to the site will be = Still to be confirmed.
N.B: We have been given prices between £1,500 and £10,000 by the electricity company so we haven't been able to confirm a realistic price yet.
Workman's/Security Guards Hut:
Basically everyone has employed workers that act as security guards and do general gardening and repairs etc. The cost of employing someone to do this is only a few pounds a week. They are normally provided with a place where they can rest and get cover from the rain and get cleaned up after a days work. We have already put the foundations in along with the necessary plumbing for a small workman's hut. We will still need to build this up above the foundations. It will be a very basic construction. This is over and above what we were originally requesting but now that we are here we see that this is an essential for
Hope Centre security. Money required to complete = Still to be confirmed.
Perimeter Walls:
At the moment we have a temporary building site type fence surrounding the whole of
Hope Centre. This has been very successful for providing some sort of security for the site however this can't be a permanent arrangement. We had hoped that Pastor Leonard would be able to try and raise the required finances to build a perimeter wall but, although he has been successful in getting trees and exoneration certificates etc, this one may be a bit of a problem for him so we would also like to try and raise the additional funds to build a very basic wall built with stones and red earth. This is pointed with cement later. This is a system that is commonly used here and can last many years. If possible we would like to be building this wall now. The additional cost for this will be = Still to be confirmed.
Out Side Cooking Area:
Cooking is normally done outside with charcoal on a small charcoal burner. It is not practical to do this inside so we will need to provide each house with a small covered area, just to the rear of each property for cooking. These will be very simple constructions and the cost of these will be = Still to be confirmed.
Outside Toilets:
Included within the are that we have built the houses on is a large piece of ground situated within the area where the trees have been planted. This will be a great area for the children to play ball games etc in the relative safety of the
Hope Centre grounds. Each of the houses will have a toilet but we have already put the foundations in, along with the required plumbing, for an outside toilet block with a shower. This will stop the children from traipsing in and out of the houses. Outside toilets are more commonly used here than inside toilets. The additional cost for this will be = Still to be confirmed.
If you are wondering why the cost of this work is much more than we had originally estimated then you can read what we wrote about this in week 28 below.
 |  | Quote: |  |  | Sent byccarr |  | |  |
| quote from Week 28
Work on Hope Centre May Have to Stop at the End of February:
Although work is progressing steadily on site we now anticipate that the work may have to stop at the end of February until more funds come in. This isn't because of a lack of giving. On the contrary the giving and support on this project has been amazing. However, we haven't yet achieved the required estimated target for funding and on top of this the recession has hit us in several ways. Cement costs have risen. Because of the poor exchange rate we are not getting as much for the British Pound. In July 08 we were getting 2,230BIF to the £1 but now we are just getting 1,772BIF to the pound. As the cement is primarily the most used material on site this is now very expensive.
There are other contributing factors such as the deeper foundations and the container taking so long to arrive that we were forced to purchase materials and tools that we had already purchased and stored in the container.
For now we are only working on four houses and primarily concentrating on two and Pastor Leonard is seeking out additional funding, if possible, from other recognised funding sources within Burundi. We will also see if the Burundi president has anything to offer when we meet with him next week.
For us it's not a problem if the work has to stop temporarily but we would rather have continuity for the workers who have shown great commitment to the project. Please keep this in your thoughts and prayers.
| |
 | |  |